Progress

Solum are now in the construction phase of the project. Solum are committed to ensuring that any changes that affect passengers, neighbours or the wider community will be communicated in good time. To receive regular updates please sign up below. If you are a station user and would like information on how the works may affect station operations, please click here.

On this page please find the latest update. If you have any questions about the works, please contact Solum on info@haywardsheathforward.co.uk or call on 08457 11 41 41.

Latest update

Footbridge works
Progress:

  • Pile caps on platforms.

  • Temporary works for bridge in car park.

Waitrose works
Progress:

  • Piling matt to be installed.

  • Guide wall to be installed for secant piling.

  • Drivers staircase operational.

  • Piling to take place.

  • Site office to be relocated.

Multi Storey Car Park works
Progress:

  • Steelwork erection to commence.

  • Cladding to staircore 1 to commence.